Highway R3 Horná Štubna bypass, SO 201, SK
Highway R3 Horná Štubna bypass, SO 201
Construction of the new railway bridge over the newly constructed highway
REQUIREMENTS
• Fastest solution for the construction of the new bridge
• Allow for the option to extend the bridge, to accommodate a future extension of the highway to 2+2 lanes
• Minimizing the risks associated with a built-in-situ structure
• A fast solution with minimum impact to the building site traffic and the environment
SOLUTION
• An alternative to massive built-in-situ abutments and the related construction processes and technologies
• Use of a frame precast system on slab raft foundation
• Using 8m high wing-walls
• Overall construction of the bridge and thus total rail possession in only 43 days
• Eliminated the requirement for a temporary bridge
• The main route was not blocked for the site traffic during installation
- CLIENT NDS a.s. (Slovak Highway Agency)
- YEAR 2009
- INSTALATION16/09/2009 – 25/09/2009, 10 days only, including wing walls
- CONTRACTORSkanska BS a.s.
- DESIGNERISPO Prešov s.r.o.
- STRUCTUREOC 13,5m x 7,0m frame precast system
- SPAN13,5m (internal)
- HEIGHT7,0m (internal)
- LENGTH33,7m (19 rings of 1,75m)